You need to set the calendars correctly for this resources assignments

You are managing a project schedule in Microsoft Office Project Standard 2007. The calendar for one of your resources has been edited to block out his vacation days. You learn that the resource’s task can be performed only on certain days, and you create a calendar indicating those days. You need to set the calendars correctly for this resources assignments. What should you do?

You are managing a project schedule in Microsoft Office Project Standard 2007. The calendar for one of your resources has been edited to block out his vacation days. You learn that the resource’s task can be performed only on certain days, and you create a calendar indicating those days. You need to set the calendars correctly for this resources assignments. What should you do?

A.
Assign the new calendar to the task.

B.
Create a vacation exception on the project calendar.

C.
Change the resource calendar to match the task calendar.

D.
Modify the resource calendar so that it will override the task calendar.



Leave a Reply 0

Your email address will not be published. Required fields are marked *