You are managing a project schedule in Microsoft Office Project Standard 2007. A task assigned to a resource will take 10 hours to complete. Due to other project commitments, he requires 3 weeks to complete the task and will not finish early. The project schedule is based on a Monday-to-Friday work week and an 8-hour work day. You need to set up the task to correctly represent the available information. What should you do first?
A.
Create a fixed units task that has a Work value of 10 hours.
B.
Create a fixed work task that has a Work value of 10 hours.
C.
Create a fixed duration task that has a Work value of 10 hours.
D.
Create a fixed duration, non effort-driven task that has a Work value of 30 hours.