You need to track project expenditures for each task on the project schedule

You are managing a project schedule in Microsoft Office Project Standard 2007. You have several team members who will be spending money on tasks they are assigned to. You need to track project expenditures for each task on the project schedule. What should you do?

You are managing a project schedule in Microsoft Office Project Standard 2007. You have several team members who will be spending money on tasks they are assigned to. You need to track project expenditures for each task on the project schedule. What should you do?

A.
Enter the expenditures as line items in each resources cost rate tables.

B.
Set the cost per use for each resource to the amount of the expenditure.

C.
Create a cost resource, and assign it to each task in your schedule that incurs costs. Update the value of the assignment when you receive updated cost information from your team.

D.
Create a cost resource with a Budget attribute of Yes, and assign it to the project summary task.
Update the budgeted cost of the assignment when you receive updated cost information from your team.