The project you are creating in Microsoft Office Project Standard 2007 includes a task with definite deadlines. Completing the task work by the deadline requires two resources with specific skills. Only one resource with these skills is available. You need to submit the schedule tomorrow with this task allocated to two resources. What should you do?
A.
Use a cost resource as the second resource.
B.
Use a generic resource as the second resource.
C.
Use a material resource as the second resource.
D.
Divide the task into two tasks, and then apply the same resource twice.