You are managing a project schedule in Microsoft Office Project Standard 2007. You create a fixed units task with a duration of 2 days. You have not yet assigned resources to the task. You need to increase the task duration to 4 days, and ensure that the effort associated with the task does not change. What should you do?
A.
Change the work amount to 4 days.
B.
Change the task duration to 4 days.
C.
Change the task type to fixed work, and set the work amount to 16 hours.
D.
Change the task type to fixed duration, and set the work amount to 32 hours.