You are tracking a project in Microsoft Office Project Standard 2007. One of the resources assigned to the project has left the company. You need to remove the resource from your schedule without removing any of the Actual Work data that he has reported. What should you do first?
A.
Use the Replace Resource feature to replace the current resource for all tasks.
B.
Use the Remove Resource feature to delete the current resource from all tasks.
C.
With Resource Name displayed in the Resource Sheet view, delete the resources name.
D.
With Resource Name displayed in the Resource Usage view, delete the resources name.