You are creating a project plan in Microsoft Office Project Standard 2007. Your resources work 8 hours a day, 5 days a week. A fixed duration, effort-driven task with 80 hours of work has one resource assigned to it at 50%. The schedule changes, and the task now must be completed in 5 days. You need to ensure that the task is completed in 5 days. What should you do?
A.
Assign an additional resource to work on the task full time.
B.
Assign two additional resources to work on the task, entering a Units value of 50%.
C.
Change the task type to fixed work, assign the original resource to work on the task full time, and set a Finish No Later Than constraint on the task.
D.
Change the task type to fixed work, set the original resource units to 100%, and then assign another resource to work on the task full time.