You need to ascertain whether the resource is overallocated during the first month of the schedule

You are developing a project schedule in Microsoft Office Project Standard 2007. The project uses a shared resource pool. One of the resources assigned to the project is assigned to another project on a half-time basis during the first month of the project. You need to ascertain whether the resource is overallocated during the first month of the schedule. What should you do first?

You are developing a project schedule in Microsoft Office Project Standard 2007. The project uses a shared resource pool. One of the resources assigned to the project is assigned to another project on a half-time basis during the first month of the project. You need to ascertain whether the resource is overallocated during the first month of the schedule. What should you do first?

A.
Set the resource availability in the resource pool for that month at 0.5%.

B.
Set the resource availability in the resource pool for that month to 50%.

C.
Set the resource availability for that month at 100% and confirm the sharing agreement with the project manager of the other project.

D.
In the resources calendar, set all the working days for the first month as Nondefault Working Time, and then set them to half the hours of a default working day.