Your company tracks projects in Microsoft Office Project Standard 2007 by duration and milestones only. In the Gantt Chart view, you need to input the actual data for a project. What should you do?
A.
Update the Units field for all assignments.
B.
Update the Actual Work field for each task.
C.
Update the fields in the Update Tasks dialog box.
D.
Update the Remaining Work field for each assignment.