you need to identify which tasks are behind schedule

You are tracking a project in Microsoft Office Project Standard 2007. In the Gantt Chart view, you need to identify which tasks are behind schedule. What should you do?

You are tracking a project in Microsoft Office Project Standard 2007. In the Gantt Chart view, you need to identify which tasks are behind schedule. What should you do?

A.
Sort the tasks by start date.

B.
Group the tasks by completion status.

C.
Set the status date to the current date, and then display a progress line.

D.
Set the status date to the current date, and then open the Project Statistics dialog box.