You are tracking a project in Microsoft Office Project Standard 2007. You need to update the project with time worked per day. What should you do?
A.
Enter Work in a task view.
B.
Enter Actual Start in an assignment view.
C.
Enter Actual Work in an assignment view.
D.
Enter Physical % Complete in a task view.