You are reviewing a project schedule that you are tracking in Microsoft Office Project Standard 2007. You have saved a baseline. You need to ascertain whether the milestones are on schedule. What should you do?
A.
Display the Actual Work field in the Tracking table.
B.
Display the Actual Work field in the Baseline table.
C.
Display the Start Variance field in the Variance table.
D.
Display the Actual Start Date field in the Tracking table.