You have a project plan which was created using Microsoft Office Project Standard 2007. You need to create a presentation of project status which will allow you to dynamically change the timescale and fields which are displayed. What should you do?
A.
Create a visual report.
B.
Create a custom basic report.
C.
Paste a picture of the Gantt chart into a visual presentation.
D.
Filter the project plan to display only critical tasks, and then paste a copy of the table into a visual presentation.