You need to select the appropriate view in which to update your project with resource hours worked per week

You are tracking a project in Microsoft Office Project Standard 2007. You need to select the appropriate view in which to update your project with resource hours worked per week. What should you do?

You are tracking a project in Microsoft Office Project Standard 2007. You need to select the appropriate view in which to update your project with resource hours worked per week. What should you do?

A.
Display the project schedule in the Tracking Gantt view.

B.
Display the project schedule in the Resource Graph view.

C.
Display the project schedule in the Resource Sheet view, and then display the Work table.

D.
Display the project schedule in the Resource Usage view, and then add the Actual Work row.