You are editing a schedule in Microsoft Office Project Standard 2007, scheduling from the start of the project. You notice that Task X is starting later than you expected. Task W is 100 percent complete. You need Task X to start on Tuesday. Which dependency should you delete?
A.
The dependency between Task A and the summary task.
B.
The dependency between Task W and Task X.
C.
The dependency between Task X and Task Y.
D.
The dependency between Task Z and Task X.