You are tracking a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: You need to ascertain the late finish of Task 4. What is the result?
A.
The end of Week 1.
B.
The end of Week 2.
C.
The end of Week 3.
D.
The end of Week 4.