You need to decrease the project duration

You are tracking a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: All tasks are set to fixed work. Only the resources shown in the above project plan are assigned to the tasks. Both resources have the same skill set. You need to decrease the project duration. What should you do?

You are tracking a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: All tasks are set to fixed work. Only the resources shown in the above project plan are assigned to the tasks. Both resources have the same skill set. You need to decrease the project duration. What should you do?

A.
Reschedule Task 4 to Week 2.

B.
Assign Maria at 100% to Task 2.

C.
Assign Maria at 100% to Task 4.

D.
Assign Teodor at 150% to Task 4.