You are tracking a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: You need to predict the effect of changing the duration of Task 2 to two weeks. What is the result?
A.
Task 2 will finish in Week 4.
B.
Task 4 will finish in Week 4.
C.
Task 1 will be non-critical, and the project will finish in Week 3.
D.
Task 4 will be non-critical, and the project will finish in Week 4.