You need to predict the effect of changing the duration of Task 2 to two weeks

You are tracking a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: You need to predict the effect of changing the duration of Task 2 to two weeks. What is the result?

You are tracking a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: You need to predict the effect of changing the duration of Task 2 to two weeks. What is the result?

A.
Task 2 will finish in Week 4.

B.
Task 4 will finish in Week 4.

C.
Task 1 will be non-critical, and the project will finish in Week 3.

D.
Task 4 will be non-critical, and the project will finish in Week 4.