You need to create a multi-level Work Breakdown Structure (WBS) that includes all deliverables and tasks

You are tracking a project in Microsoft Office Project Standard 2007. The project includes multiple deliverables, each broken down into multiple tasks. You need to create a multi-level Work Breakdown Structure (WBS) that includes all deliverables and tasks. What should you do?

You are tracking a project in Microsoft Office Project Standard 2007. The project includes multiple deliverables, each broken down into multiple tasks. You need to create a multi-level Work Breakdown Structure (WBS) that includes all deliverables and tasks. What should you do?

A.
Distribute costs to the deliverables and resources to the tasks.

B.
Enter the deliverables, and then indent their associated tasks.

C.
Enter the deliverables, and then enter the tasks in the Notes field.

D.
Enter the deliverables, and then add dependencies to their associated tasks.