What should you do?

In Microsoft Office Project Standard 2007, you are tracking a project for which the overall duration might change. A resource who works 8 hours a day, 5 days a week, spends 2 hours a day creating reports for the project. You need the project schedule to reflect this estimated reporting work. What should you do?

In Microsoft Office Project Standard 2007, you are tracking a project for which the overall duration might change. A resource who works 8 hours a day, 5 days a week, spends 2 hours a day creating reports for the project. You need the project schedule to reflect this estimated reporting work. What should you do?

A.
Create a fixed duration task of 1 week. Enter 20 hours of work for each week of the project. Assign the resource to the task at 100%.

B.
Create a fixed units task, and link the task start and finish dates to the project start and finish dates. Assign the resource to the task at 25%.

C.
Create a fixed work task, entering 2 hours of work, and link the task start and finish dates to the project start and finish dates. Assign the resource to the task at 100%.

D.
Create a fixed duration task, entering 2 hours of work, and link the task start and finish dates to the project start and finish dates. Assign the resource to the task at 100%.