What task type should you use?

You are managing a project schedule in Microsoft Office Project Standard 2007. A scheduled task requires 100 hours of work and has a duration of 10 days. One resource is available to do the work, but you might get another. You need to set up the task so that if you add another resource, the new resource will share the hours with the original resource and the finish date will remain the same.
What task type should you use?

You are managing a project schedule in Microsoft Office Project Standard 2007. A scheduled task requires 100 hours of work and has a duration of 10 days. One resource is available to do the work, but you might get another. You need to set up the task so that if you add another resource, the new resource will share the hours with the original resource and the finish date will remain the same.
What task type should you use?

A.
fixed work

B.
fixed units, effort-driven

C.
fixed duration, effort-driven

D.
fixed duration, non effort-driven



Leave a Reply 0

Your email address will not be published. Required fields are marked *