You use Microsoft Office Project Standard 2007 to track your project schedule. You assign a resource to tasks scheduled during normal working hours. Starting the first of next month, the hourly rate of this resource will increase by 20 percent. Without changing any of the resource’s assignments, you need to ensure that your project costs reflect the new hourly rate. What should you do?
A.
Edit the resources Cost Rate tables to show a cost per use of +20% effective on the first day of next month.
B.
Edit the resources Cost Rate tables to show a standard cost of +20% effective on the first day of next month.
C.
Filter the tasks to display only those that utilize the resource. For each task, add a fixed cost of 20 percent of the current cost of the task.
D.
Create a resource with a standard cost that is 20 percent of the existing resources standard cost.
Then allocate a duplicate of all of the existing resource’s assignments to the new resource.