You need to update the schedule to reflect the new Resource B work estimate

You are tracking a project in Microsoft Office Project Standard 2007. Resources A and B are each assigned to work 40 hours on a task. After each resource works 30 hours, you update the schedule to reflect the actual work to date. Resource B estimates that she will need to work a total of 50 hours to complete her task assignment. You need to update the schedule to reflect the new Resource B work estimate. What should you do?

You are tracking a project in Microsoft Office Project Standard 2007. Resources A and B are each assigned to work 40 hours on a task. After each resource works 30 hours, you update the schedule to reflect the actual work to date. Resource B estimates that she will need to work a total of 50 hours to complete her task assignment. You need to update the schedule to reflect the new Resource B work estimate. What should you do?

A.
Set the Work value for the task to 50.

B.
Set the Remaining Work value for the task to 50.

C.
Set the Work value for the resource assignment to 20.

D.
Set the Remaining Work value for the resource assignment to 20.



Leave a Reply 0

Your email address will not be published. Required fields are marked *