In Microsoft Office Project Standard 2007, you create a project plan for managing one-hour meetings that are part of a project. For each meeting, you create one task with a resource assignment for each attendee. You need to ensure that all meeting tasks show that more work is required for meetings when additional resources attend. What type of task should you set as the default?
A.
fixed work
B.
fixed units and effort-driven
C.
fixed duration and effort-driven
D.
fixed units and non effort-driven