You need to ensure that the resources assigned to this task are scheduled to work during the night shift

You are creating a project schedule in Microsoft Office Project Standard 2007. One of the five project tasks can be worked on only at night. You need to ensure that the resources assigned to this task are scheduled to work during the night shift. What should you do?

You are creating a project schedule in Microsoft Office Project Standard 2007. One of the five project tasks can be worked on only at night. You need to ensure that the resources assigned to this task are scheduled to work during the night shift. What should you do?

A.
Set the appropriate overnight working times as an exception in the project calendar.

B.
Set the appropriate overnight working times as an exception in the Night Shift calendar.

C.
Apply the Night Shift calendar to the task, and then ensure that the task is effort-driven with Standard resource calendars.

D.
Apply the Night Shift calendar to the task, and then ensure that Project will ignore resource calendars when scheduling the task.