You are tracking a project in Microsoft Office Project Standard 2007. You monitor the project status by reviewing the following data: Actual start and finish datesScheduled start and finish datesCostsWork Task durations You need to display all of this project information in one window.
What should you do?
A.
Display the Summary table.
B.
Display the project schedule in the default Tracking Gantt view.
C.
Display the project statistics from the Properties dialog box.
D.
Display the project statistics from the Project Information dialog box.