You need to save the new template without including completed work data from the existing project

Using Microsoft Office Project Standard 2007, you are creating a project template from an existing project. You need to save the new template without including completed work data from the existing project. What should you do?

Using Microsoft Office Project Standard 2007, you are creating a project template from an existing project. You need to save the new template without including completed work data from the existing project. What should you do?

A.
Save the project as a template, selecting only the Actual Values option.

B.
Save the project as a template, selecting only the Values of all baselines option.

C.
Clear the baseline and then save the file as a template, using the default settings.

D.
Delete the values in the Duration column and then save the file as a template, using the default settings.



Leave a Reply 0

Your email address will not be published. Required fields are marked *