You are using Microsoft Office Project Standard 2007 to manage a construction project schedule. The construction crew is renting a portable building for the current project phase and the next phase. The two phases overlap by approximately two months. You need to include the portable building and its cost in your project schedule. What should you do?
A.
Assign the portable building as a resource to both of the phase summary tasks.
B.
Create a recurring monthly task, and then assign the rental cost of the portable building to that task.
C.
Create an ordinary task, assign the portable building to the task as a resource, and then level the project by using the resource leveling function.
D.
Assign the portable building to a new task. Link the task start date to the first phase start date and the task finish date to the second phase finish date.