You are creating a schedule in Microsoft Office Project Standard 2007. A project phase represented by Summary Task B should finish at the same time as Task A . You need to model the relationship between these tasks. What should you do?
A.
Create a start-to-finish dependency from Task A to Summary Task B.
B.
Create a finish-to-finish dependency from Task A to Summary Task B.
C.
Create a finish-to-finish dependency from Summary Task B to Task A.
D.
Create a finish-to-finish dependency from Task A to the final task of Summary Task B.