You are tracking a project in Microsoft Office Project Standard 2007. The project uses the default Standard working calendar. You have entered deadlines for several tasks. In the project calendar, there are both working days and nonworking days between the tasks finish and deadline dates. You need to set up a method to automatically calculate the number of working days between the tasks finish dates and deadline dates. What should you do?
A.
Customize a number field by using the ([Deadline]-[Finish])/1000 formula.
B.
Customize a duration field by using the ([Deadline]-[Finish])/1000formula.
C.
Customize a number field by using the ProjDateDiff([Finish],[Deadline])/480 formula.
D.
Customize a number field by using the(DateValue([Deadline])-DateValue([Finish]))/480formula.