In Microsoft Office Project Standard 2007, you are tracking a project by duration. The Updating task status updates resource status option is not activated. You need to display the current status of the project. What should you display?

In Microsoft Office Project Standard 2007, you are tracking a project by duration. The Updating task status updates resource status option is not activated. You need to display the current status of the project. What should you display?

A.
The % Work Complete field in the Project Statistics dialog box.

B.
The % W. Complete field for the project summary task in the task Work table.

C.
The % Complete field for the project summary task in the task Tracking table.

D.
The Physical % Comp. field for the project summary task in the task Tracking table.