The project schedules you manage in Microsoft Office Project Standard 2007 all follow standard project lifecycle phases. You need to be able to display all tasks of all projects by phase. What should you do?

The project schedules you manage in Microsoft Office Project Standard 2007 all follow standard project lifecycle phases. You need to be able to display all tasks of all projects by phase. What should you do?

A.
Within a master project that contains all projects, create a summary task for each phase, and then display all tasks.

B.
Create a project plan template with the standard project lifecycle phases as summary tasks. Use this plan template for all projects.

C.
Create a shared resource pool, associate the resource pool with all projects, assign resources to summary tasks that represent phases, and then display all tasks.

D.
Within a master project that contains all projects, create a custom task text field with a value for each phase, associate all tasks with one of the values, and then group all tasks by this field.