You are managing a project in Microsoft Office Project Standard 2007. The project follows the plan shown below: Task 1 is 100 percent complete. Tasks 2 and 4 are each 50 percent complete. The forecast duration of Task 2 is half a week more than its baseline duration. Task 3 cannot start until Task 2 is complete. Task 4 is 1 week late. You need to modify the schedule to meet the original finish date. What should you do?
A.
Clear the existing baseline, and then set a new baseline.
B.
Assign extra resources to Task 4 to eliminate the 1-week delay.
C.
Assign extra resources to Task 2 to eliminate the forecast increase in the duration.
D.
Delete the link between Tasks 2 and 3. Then change Task 1 to a predecessor of Task 3, so that Task 3 can start ahead of time.