You need to forecast when the project will need resources with specific skills

You are creating a schedule in Microsoft Office Project Professional 2007. For budgeting purposes, you allocate resources 6 months in advance of the project. You do not know who will be assigned to your project at this time. You need to forecast when the project will need resources with specific skills. What should you do?

You are creating a schedule in Microsoft Office Project Professional 2007. For budgeting purposes, you allocate resources 6 months in advance of the project. You do not know who will be assigned to your project at this time. You need to forecast when the project will need resources with specific skills. What should you do?

A.
Assign work resources to tasks and use the default Calendar view.

B.
Assign work resources to tasks and use the default Network Diagram view.

C.
Assign generic resources to tasks and use the default Resource Sheet view.

D.
Assign generic resources to tasks and use the default Resource Graph view.