You need to immediately display the effect of your changes on the start and finish dates of other tasks

In Microsoft Office Project Standard 2007, you are changing the durations of several tasks in a project schedule. You need to immediately display the effect of your changes on the start and finish dates of other tasks. What should you do?

In Microsoft Office Project Standard 2007, you are changing the durations of several tasks in a project schedule. You need to immediately display the effect of your changes on the start and finish dates of other tasks. What should you do?

A.
Display the entire project in a network diagram.

B.
Use Change Highlighting to show changed dates.

C.
Set the Highlighted Tasks text style to a contrasting color.

D.
Filter the project to show tasks that have changed from the baseline schedule.



Leave a Reply 0

Your email address will not be published. Required fields are marked *