In Microsoft Office Project Web Access, you create an activity plan with a resource plan for a simple project. The plan is currently saved, but not published, to Microsoft Office Project Server 2007. You need to identify which tasks have assigned resources. What should you do?

In Microsoft Office Project Web Access, you create an activity plan with a resource plan for a simple project. The plan is currently saved, but not published, to Microsoft Office Project Server 2007. You need to identify which tasks have assigned resources. What should you do?

A.
In the activity plan, review the resource assignments.

B.
In the resource plan, review the committed resources.

C.
On the Resource Center page, review the team assignments.

D.
On the Resource Center page, review the resource assignments.