You need to capture the types of resources and the estimated effort required from these resources over the duration of the project

You have created a proposal in Microsoft Office Project Web Access. Some of your resources will be working part time. You need to capture the types of resources and the estimated effort required from these resources over the duration of the project. What should you do?

You have created a proposal in Microsoft Office Project Web Access. Some of your resources will be working part time. You need to capture the types of resources and the estimated effort required from these resources over the duration of the project. What should you do?

A.
Use the team builder to add resources to the proposal, assign them to tasks, and then publish the proposal.

B.
Publish the proposal, and create a resource plan. Then use the team builder to add resources, and publish the resource plan.

C.
Use the team builder to add generic resources to the proposal, assign them to tasks, and then publish the proposal.

D.
Change the resource utilization to calculate from the resource plan.