You manage several resources who report both project and operational work.
The projects, which are tracked on the project level, are published to Microsoft Office Project Server 2007. The operational work is published as activities. You need to review the reported work. What should you do?
A.
In Microsoft Office Project Web Access, review the status reports of your resources.
B.
In Microsoft Office Project Web Access, review the task updates of your resources.
C.
In Microsoft Office Project Web Access, review the timesheets of your resources.
D.
In Microsoft Office Project Professional 2007, review the updates to each project.