You need to inform the project sponsor about this progress

You are working on a project that is saved to Microsoft Office Project Server 2007. In the past 2 days, your project team has made significant progress on a task, but it is still not complete. You need to inform the project sponsor about this progress. What should you do?

You are working on a project that is saved to Microsoft Office Project Server 2007. In the past 2 days, your project team has made significant progress on a task, but it is still not complete. You need to inform the project sponsor about this progress. What should you do?

A.
In Microsoft Office Project Professional 2007, submit a new status report request to the project sponsor.

B.
In Microsoft Office Project Professional 2007, submit an unrequested status report to the project sponsor.

C.
In Project Server, change the status report request frequency to weekly.

D.
In Project Server, change the status report request frequency to every day.