You need to record the hours you work on assigned tasks

You are assigned to tasks in projects and in non-project activities that are published to Microsoft Office Project Server 2007. You need to record the hours you work on assigned tasks. What should you do?

You are assigned to tasks in projects and in non-project activities that are published to Microsoft Office Project Server 2007. You need to record the hours you work on assigned tasks. What should you do?

A.
In Microsoft Office Project Web Access, on the My Tasks page, create a new task for each task and activity.

B.
In Microsoft Office Project Web Access, create a timesheet for all projects worked on in the current period.

C.
In Microsoft Office Project Web Access, create a timesheet for all tasks worked on in the current period.

D.
In Microsoft Office Project Professional 2007, enter your work hours directly into the project.