You are a resource manager. One of the resources assigned to a project that is published to Microsoft Office Project Server 2007 has submitted a timesheet with incorrect actual hours for a project activity. You need to ensure that the number of hours is corrected and that a historical record of this transaction is logged. What should you do?
A.
Accept all activities, and then request a new status report from the resource.
B.
Have the resource correct the timesheet when it is imported into task updates.
C.
Reject the timesheet, and then add a comment describing the error.
D.
In Microsoft Office Project Professional 2007, update the total work for the assignment, and then save and publish the project.
Hi colleagues, its fantastic piece of writing regarding tutoringand entirely defined, keep it up all the time.