You need to ensure that the number of hours is corrected and that a historical record of this transaction is logged

You are a resource manager. One of the resources assigned to a project that is published to Microsoft Office Project Server 2007 has submitted a timesheet with incorrect actual hours for a project activity. You need to ensure that the number of hours is corrected and that a historical record of this transaction is logged. What should you do?

You are a resource manager. One of the resources assigned to a project that is published to Microsoft Office Project Server 2007 has submitted a timesheet with incorrect actual hours for a project activity. You need to ensure that the number of hours is corrected and that a historical record of this transaction is logged. What should you do?

A.
Accept all activities, and then request a new status report from the resource.

B.
Have the resource correct the timesheet when it is imported into task updates.

C.
Reject the timesheet, and then add a comment describing the error.

D.
In Microsoft Office Project Professional 2007, update the total work for the assignment, and then save and publish the project.



Leave a Reply 1

Your email address will not be published. Required fields are marked *


project 2010 key

project 2010 key

Hi colleagues, its fantastic piece of writing regarding tutoringand entirely defined, keep it up all the time.