In a project that is published to Microsoft Office Project Server 2007, your resources submit their progress updates to you for approval. You are leaving on vacation for 2 weeks.
You need to ensure that another project manager can approve resource task updates while you are gone.
What should you do?
A.
In Microsoft Office Project Web Access, create surrogate timesheets for your resources before you leave on vacation.
B.
In Microsoft Office Project Web Access, on the Resource Center page, change the timesheet manager for your resources to the other project manager.
C.
In Microsoft Office Project Professional 2007, set the assignment owner for all project tasks to the temporary project manager.
D.
In Microsoft Office Project Professional 2007, set the status manager for all project tasks to the temporary project manager.