You manage a set of projects that are saved to Microsoft Office Project Server 2007. You have been asked to generate a report for each project that displays the work performed by day and that can be filtered based on a customer custom field. In Microsoft Office Project Web Access, you need to create this view. What should you do?
A.
On the Project Center page, create a view that contains the customer custom field so that it can be filtered.
B.
On the Project Center page, create a view in which the customer custom field has Show Date and Time enabled.
C.
On the Data Analysis page, create a view that displays baseline work information by day and project with the customer custom field as a filter value.
D.
On the Data Analysis page, create a view that displays actual work information by day and project with the customer custom field as a filter value.