In a project that is published to Microsoft Office Project Server 2007, your resources enter actual work and remaining work for their tasks and submit the updates to you. You need to see the impact of these updates in Microsoft Office Project Web Access before accepting them. What should you do?
A.
On the Task Updates page, preview the updated tasks.
B.
On the Data Analysis page, add the project data to the pivot table.
C.
Display the Project Details page in the default Tasks Schedule view.
D.
Display the Project Center page in the default Tracking view.