You need to add some deliverables to your project tasks

You create and save a project schedule in Microsoft Office Project Professional 2007. You need to add some deliverables to your project tasks. However, the Manage Deliverables feature is not available. What should you do?

You create and save a project schedule in Microsoft Office Project Professional 2007. You need to add some deliverables to your project tasks. However, the Manage Deliverables feature is not available. What should you do?

A.
Publish the project plan with a project workspace site.

B.
Save the project plan as a workspace.

C.
Save the project plan to a project workspace site.

D.
Use the Manage Dependencies on Deliverables feature.