Where can you compare this information?

You publish all project plans for the next fiscal year to Microsoft Office Project Server 2007. You assign generic resources to the tasks of these project plans. Each named resource in your organization is associated with one role. Each role maps to one of the generic resource names. In Microsoft Office Project Web Access, you need to compare the utilization of all generic resources with the availability of all named resources. Where can you compare this information?

You publish all project plans for the next fiscal year to Microsoft Office Project Server 2007. You assign generic resources to the tasks of these project plans. Each named resource in your organization is associated with one role. Each role maps to one of the generic resource names. In Microsoft Office Project Web Access, you need to compare the utilization of all generic resources with the availability of all named resources. Where can you compare this information?

A.
On the Resource Assignments page

B.
On the Project Center page

C.
On the Resource Center page

D.
On the Data Analysis page



Leave a Reply 0

Your email address will not be published. Required fields are marked *