You have a project plan with resources that are associated with one of two calendars: one for a country where resources work 39 hours per week, and one for a country where resources work 38 hours per week. You import the project plan into Microsoft Office Project Server 2007. After the import, you notice that the dates of the tasks are different. You need to make sure that the dates are set to the way they were before the import. You create one enterprise calendar for each country. What should you do next?
A.
Assign the calendar of 39 hours to the project.
B.
Assign the calendar of 38 hours to the project.
C.
Assign the calendars to the resources based on the tasks of the resources.
D.
Assign the calendars to the resources based on the country of the resources.