You are working in Microsoft Office Project Web Access on an activity plan. Task B must not start until after Task A has started. You need to link the tasks in such a way that Task B can start any time after Task A starts. What should you do?
A.
Link the tasks in the activity plan.
B.
Set the start of Task B to be the same as Task A in the activity plan.
C.
Promote the activity to a project, and then in Microsoft Office Project Professional 2007, link the tasks.
D.
Promote the activity to a project, and then in Microsoft Office Project Professional 2007, link Task B to a deliverable associated with Task A.
You have published an awesome resource.