You are working in Microsoft Office Project Web Access on an activity plan in which Task A and Task B are not linked. However, Task B cannot start until Task A is complete. You need to link the two tasks so that Task B starts when Task A is complete. What should you do?
A.
Set the start date for Task B equal to the finish date for Task A.
B.
Set the start date for Task B to a date after the finish date for Task A.
C.
Set Task B as the predecessor for Task A.
D.
Set Task A as the predecessor for Task B.