you need to ensure that the bonus date for the task is marked in Gantt Chart views

In a project plan that is published to Microsoft Office Project Server 2007, a task has a finish date of July 15. If your team completes the task by July 12, team members will get a performance bonus. The bonus date is not a hard constraint, but it should be clearly indicated in the project plan. Using Microsoft Office Project Professional 2007, you need to ensure that the bonus date for the task is marked in Gantt Chart views. What should you do?

In a project plan that is published to Microsoft Office Project Server 2007, a task has a finish date of July 15. If your team completes the task by July 12, team members will get a performance bonus. The bonus date is not a hard constraint, but it should be clearly indicated in the project plan. Using Microsoft Office Project Professional 2007, you need to ensure that the bonus date for the task is marked in Gantt Chart views. What should you do?

A.
Set a Finish No Later Than constraint on the task, and then set the finish date.

B.
Set a Must Finish On constraint on the task, and then set the finish date.

C.
Enter the bonus date as a deadline.

D.
Create a cost resource to represent the bonus.